DATE |
EVENT |
November 14, 2008 |
NEPA Pre-Filing Application |
June 15, 2009 |
File FERC Application |
December 17, 2009 |
Received FERC Certificate |
January 25, 2010 |
Compressor Station - Construction Begins |
March 5, 2010 |
Pipeline - Received Final FERC Notice to Proceed |
March 2010 |
Pipeline - Construction Begins (1160 MAOP) |
April 2010 |
Pipeline - Construction Begins (1480 MAOP) |
May 2010 |
Meter Stations - Construction Begins |
October 2010 |
Interim-Service to NGPL |
End of Q4 2010 |
Full In-Service |
|